Public Works Complex
Federal contribution
$743,333
Federal share33%
of $2.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Blind River
- Construction start
- Mar 1, 2010(actual)
- Construction end
- Nov 16, 2010(actual)
Against the original forecast
- Construction start4 months lateforecast Nov 1, 2009
- Construction end3 months lateforecast Aug 31, 2010
Also in Blind River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31787 in the federal list. How to read these figures.