Public Works Complex

Blind River, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$743,333
Federal share33%

of $2.2M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Town of Blind River
Construction start
Mar 1, 2010(actual)
Construction end
Nov 16, 2010(actual)

Against the original forecast

  • Construction start4 months lateforecast Nov 1, 2009
  • Construction end3 months lateforecast Aug 31, 2010