Sewage Treatment Plant Upgrades
Federal contribution
$669,921
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 12, 2015
201620172018
Built
Approved 8 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Blind River
- Construction start
- Jun 20, 2016(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction start7 weeks lateforecast May 1, 2016
- Construction end3 months lateforecast Dec 31, 2017
Also in Blind River
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46177 in the federal list. How to read these figures.