Sewage Treatment Plant Upgrades

Blind River, Ontario

completeWastewaterSCF
Federal contribution
$669,921
Federal share33%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 12, 2015
201620172018
Built

Approved 8 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Town of Blind River
Construction start
Jun 20, 2016(actual)
Construction end
Mar 31, 2018(actual)

Against the original forecast

  • Construction start7 weeks lateforecast May 1, 2016
  • Construction end3 months lateforecast Dec 31, 2017