Back to projects

Revitalization of the Algonquin Warehouse Equipment Maintenance Garage

Augusta, Ontario

completeAdministration, Emergency and Public WorksISF
Federal contribution
$150,000
Federal share33%

of $450.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Augusta
Construction start
Oct 10, 2010(actual)
Construction end
Oct 27, 2011(actual)

Against the original forecast

  • Construction start6 months lateforecast Apr 1, 2010
  • Construction end3 months lateforecast Jul 31, 2011

Also in Augusta