Augusta Public Works Building Renovations
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
20222023
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Township of Augusta
- Construction start
- May 1, 2023(actual)
- Construction end
- Nov 15, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Apr 3, 2023
- Construction end4 months lateforecast Jul 3, 2023
Also in Augusta
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59368 in the federal list. How to read these figures.