Sidewalk Rehabilitation
Federal contribution
$980,504
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Guelph
- Construction start
- Mar 29, 2010(actual)
- Construction end
- Sep 30, 2011(actual)
Against the original forecast
- Construction start7 months lateforecast Sep 1, 2009