Road Rehabilitation - Regional Road 60
Federal contribution
$183,333
Federal share33%
of $550.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Durham
- Construction start
- Sep 27, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Aug 30, 2010
- Construction end4 months earlyforecast Mar 31, 2011
Also in Oshawa
- Oshawa Civic Complex Renewal and Expansion$6.2M
- WIFI Access Points; Window replacement; HVAC Upgrades; Bottle Water Filling Stations; Sink replacements$5.6M
- Harmony Creek Trail extension in Oshawa ON$1.5M
- Storm Water Management Pond Cleaning by removal and disposal of sediment at 10 locations.$582.2K
- Gym Partition; Accessible door operators; Expand shared kindergarten and childcare outdoor space$312.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31806 in the federal list. How to read these figures.