Storm Water Management Pond Cleaning by removal and disposal of sediment at 10 locations.

Oshawa, Ontario

completeWastewaterCWWF
Federal contribution
$582,170
Federal share45%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
2018
Built

Approved 3 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
City of Oshawa
Construction start
Aug 1, 2017(actual)
Construction end
Sep 30, 2018(actual)

Against the original forecast

  • Construction start3 months earlyforecast Nov 1, 2017
  • Construction end4 weeks lateforecast Sep 1, 2018