Downtown Streetscape Redevelopment
Federal contribution
$272,021
Federal share80%
of $340.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
2022
Built
Approved 5 weeks before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- City of Oshawa
- Construction start
- Oct 18, 2021(actual)
- Construction end
- Jul 30, 2022(actual)
Against the original forecast
- Construction start5 weeks lateforecast Sep 13, 2021
Also in Oshawa
- Oshawa Civic Complex Renewal and Expansion$6.2M
- WIFI Access Points; Window replacement; HVAC Upgrades; Bottle Water Filling Stations; Sink replacements$5.6M
- Harmony Creek Trail extension in Oshawa ON$1.5M
- Storm Water Management Pond Cleaning by removal and disposal of sediment at 10 locations.$582.2K
- Gym Partition; Accessible door operators; Expand shared kindergarten and childcare outdoor space$312.0K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60050 in the federal list. How to read these figures.