McLennan Park Development
Federal contribution
$1.0M
$1,000,000
Federal share33%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Kitchener
- Construction start
- Jul 1, 2010(actual)
- Construction end
- Aug 31, 2011(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Sep 30, 2011
Also in Kitchener
- Stormwater Network Adaptation$50.0M
- Aquatic Centre RBJ Schlegel Park$9.8M
- Installing mechanical ventilation in buildings where none currently exist; Window repair or replacement for fresh air intake$7.9M
- HVAC Upgrades; Upgrading wireless access points; Window replacement; Washroom upgrades; Installing cooling / air conditioning units; room partition replacement$7.6M
- Kitchener Public Library Southwest Community Library$6.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31813 in the federal list. How to read these figures.