West Street Rehabilitation
Federal contribution
$416,054
Federal share28%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of Ignace
- Construction start
- Jul 13, 2010(actual)
- Construction end
- Oct 21, 2011(actual)
Against the original forecast
- Construction start3 weeks lateforecast Jun 21, 2010
Also in Ignace
- Lakeshore Drive Rehabilitation$513.3K
- Rehabilitation of Pine Street$380.5K
- Ignace Water Conservation$194.7K
- Sewer Main upgrade, with replacement of asbestos pipe to new 200 mm Polyvinyl chloride (PVC) main and storm sewer main$134.7K
- Sewer Main upgrade, with replacement of one sewer main approximately 170 meters long and replacement of one sewer main approximately 50 meters long$123.5K
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31843 in the federal list. How to read these figures.