Sewer Main upgrade, with replacement of one sewer main approximately 170 meters long and replacement of one sewer main approximately 50 meters long
Federal contribution
$123,484
Federal share48%
of $255.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 24, 2017
2018
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Township of Ignace
- Construction start
- Oct 30, 2017(actual)
- Construction end
- Jul 20, 2018(actual)
Against the original forecast
- Construction start2 months lateforecast Aug 21, 2017
- Construction end6 weeks earlyforecast Aug 31, 2018
Also in Ignace