Dalhousie Street Reconstruction
Federal contribution
$666,666
Federal share33%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Amherstburg
- Construction start
- Aug 30, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 16, 2010
- Construction end4 weeks earlyforecast Dec 31, 2010
Also in Amherstburg
- Construction of the Amherstburg Multi-Use Recreation Complex$7.8M
- Upgrading of the Amherstburg Pollution Control Plant$5.3M
- Edgewater Sewage Diversion$2.9M
- Pump Station Upgrades, Forcemain Installation and Edgewater Lagoon Decommissioning$2.5M
- Amherstburg Water Treatment Plant Reservoir Rehabilitation$2.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31870 in the federal list. How to read these figures.