Edinburgh Road - Speedvale to London
Federal contribution
$823,686
Federal share33%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Guelph
- Construction start
- Jun 28, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 30, 2010
- Construction end4 weeks lateforecast Sep 30, 2011