Intersection - Speedvale/Stevenson
Federal contribution
$781,148
Federal share31%
of $2.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Guelph
- Construction start
- Apr 26, 2010(actual)
- Construction end
- Oct 27, 2010(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Nov 30, 2010
Also in Guelph
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31885 in the federal list. How to read these figures.