Victoria Road North - Ferndale to City Limit

Guelph, Ontario

completeHighways and RoadsISF
Federal contribution
$800,000
Federal share33%

of $2.4M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Guelph
Construction start
Jun 24, 2010(actual)
Construction end
Nov 26, 2010(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 30, 2010
  • Construction end5 weeks earlyforecast Dec 31, 2010