Victoria Road South

Guelph, Ontario

completeHighways and RoadsISF
Federal contribution
$605,289
Federal share24%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Guelph
Construction start
Apr 21, 2010(actual)
Construction end
Nov 1, 2010(actual)

Against the original forecast

  • Construction end2 months earlyforecast Dec 31, 2010

Also in Guelph

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 31902 in the federal list. How to read these figures.