Intersection Improvement - Victoria and Eastview
Federal contribution
$373,984
Federal share25%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Guelph
- Construction start
- Apr 21, 2010(actual)
- Construction end
- Nov 1, 2010(actual)
Against the original forecast
- Construction start3 weeks lateforecast Apr 1, 2010
- Construction end2 months earlyforecast Dec 31, 2010