Intersection - Victoria/Woodlawn

Guelph, Ontario

completeHighways and RoadsISF
Federal contribution
$331,212
Federal share15%

of $2.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Guelph
Construction start
Jun 28, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Apr 30, 2010

Also in Guelph