Back to projects

Sand/salt Storage Facility

Casey, Ontario

completeHighways and RoadsISF
Federal contribution
$63,360
Federal share33%

of $190.1K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Casey
Construction start
Oct 1, 2009(actual)
Construction end
Jan 29, 2010(actual)

Against the original forecast

  • Construction start3 weeks earlyforecast Oct 22, 2009
  • Construction end4 weeks lateforecast Dec 31, 2009

Also in Casey