Efficiency Improvements to Facilities

Casey, Ontario

completeVentilationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 7, 2021
2022202320242025
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Township of Casey
Construction start
Jul 1, 2021(actual)
Construction end
Nov 30, 2024(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end4 weeks earlyforecast Dec 31, 2024