Replacement of Polybutylene Service Connections - Homestead Court

Oshawa, Ontario

completeDrinking WaterISF
Federal contribution
$58,286
Federal share32%

of $180.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 17, 2010(actual)
Construction end
Aug 7, 2010(actual)

Against the original forecast

  • Construction start6 weeks earlyforecast Jul 1, 2010
  • Construction end4 months earlyforecast Nov 30, 2010

Also in Oshawa

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32012 in the federal list. How to read these figures.