Back to projects

Reconstruction of Peterson Road

Hastings Highlands, Ontario

completeHighways and RoadsISF
Federal contribution
$580,965
Federal share28%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 30, 2010(actual)
Construction end
Aug 30, 2010(actual)

Against the original forecast

  • Construction start8 months lateforecast Sep 15, 2009
  • Construction end4 weeks earlyforecast Sep 30, 2010

Also in Hastings Highlands

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32045 in the federal list. How to read these figures.