Rehabilitation of Hastings Highlands Local Road 62
Federal contribution
$1.2M
$1,160,940
Federal share60%
of $1.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 1, 2019
2020
Built
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Municipality of Hastings Highlands
- Construction start
- May 25, 2020(actual)
- Construction end
- Aug 7, 2020(actual)
Against the original forecast
- Construction start10 months lateforecast Aug 1, 2019
- Construction end3 months earlyforecast Oct 30, 2020
Also in Hastings Highlands