Back to projects

Bathurst Clark Library Retrofit

Vaughan, Ontario

completeCultureISF
Federal contribution
$133,334
Federal share33%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
City of Vaughan
Construction start
Aug 23, 2010(actual)
Construction end
Nov 5, 2010(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2010
  • Construction end4 weeks lateforecast Oct 7, 2010

Also in Vaughan