Don and Humber Trail System
Federal contribution
$100,000
Federal share33%
of $300.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Vaughan
- Construction start
- Oct 20, 2009(actual)
- Construction end
- Sep 22, 2010(actual)
Against the original forecast
- Construction start7 weeks lateforecast Sep 1, 2009
- Construction end3 weeks lateforecast Sep 1, 2010
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32081 in the federal list. How to read these figures.