Taylors Bridge Replacement

Peterborough, Ontario

completeHighways and RoadsISF
Federal contribution
$195,222
Federal share28%

of $700.0K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
County of Peterborough
Construction start
Jul 26, 2010(actual)
Construction end
Aug 30, 2010(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jul 1, 2010
  • Construction end2 months earlyforecast Oct 29, 2010

Also in Peterborough

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32119 in the federal list. How to read these figures.