Taylors Bridge Replacement
Federal contribution
$195,222
Federal share28%
of $700.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built
Approved 22 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Peterborough
- Construction start
- Jul 26, 2010(actual)
- Construction end
- Aug 30, 2010(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jul 1, 2010
- Construction end2 months earlyforecast Oct 29, 2010
Also in Peterborough