Peel Heritage Complex Expansion and Revitalization
Federal contribution
$3.3M
$3,333,334
Federal share33%
of $10.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Oct 31, 2009(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start2 weeks lateforecast Oct 15, 2009
Also in Brampton
- Transit Maintenance & Storage Facility$69.9M
- Protecting our future: Flood mitigation and physical, economic, social and cultural resilience for historic downtown Brampton, on by reconstructing 600M of the concrete Etobicoke Creek bypass channel$38.9M
- 2023 Replacement Buses$25.5M
- 2020-2024 Bus Refurbishments$22.2M
- 2020 Growth Buses$18.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32130 in the federal list. How to read these figures.