County of Northumberland/United Way Emergency Management System Headquarters/Food 4 All Warehouse
Federal contribution
$458,333
Federal share33%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Northumberland
- Construction start
- Sep 30, 2009(actual)
- Construction end
- Mar 31, 2010(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 27, 2009
- Construction end5 months earlyforecast Aug 31, 2010
Also in Cobourg
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32137 in the federal list. How to read these figures.