Replacement of Polybutylene Service Connections - Labrador Drive

Pickering, Ontario

completeDrinking WaterISF
Federal contribution
$57,823
Federal share32%

of $178.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Jul 19, 2010(actual)
Construction end
Jan 6, 2011(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jun 17, 2010
  • Construction end10 months earlyforecast Oct 31, 2011