Keele Street Resurfacing
Federal contribution
$301,904
Federal share24%
of $1.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Sep 30, 2009(actual)
- Construction end
- Oct 15, 2009(actual)
Against the original forecast
- Construction end5 months earlyforecast Mar 31, 2010
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32172 in the federal list. How to read these figures.