District of Nipissing Social Services Administration Board Accommodation
Federal contribution
$900,465
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- District of Nippissing Social Services Administration Board
- Construction start
- Sep 14, 2009(actual)
- Construction end
- Jan 30, 2011(actual)
Against the original forecast
- Construction end4 months lateforecast Sep 24, 2010
Also in North Bay