Replacement of Polybutylene Service Connections - Cowan Crescent and Eastlawn Street

Pickering, Ontario

completeDrinking WaterISF
Federal contribution
$57,866
Federal share33%

of $173.6K total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedMar 25, 2011
20102011
Built

Approved 22 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Apr 6, 2010(actual)
Construction end
Jan 6, 2011(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2011