Resurfacing - on the Forks of the Credit Road from Hurontario Street to West
Federal contribution
$1.2M
$1,225,669
Federal share31%
of $3.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of Peel
- Construction start
- Aug 9, 2009(actual)
- Construction end
- Jul 31, 2011(actual)
Also in Caledon
- Old Bolton Fire Hall revitalization into a low carbon, multi-purpose Community Hub as part of Caledon's downtown Bolton Revitalization Plan.$4.3M
- Belfountain Conservation Area: Dam & Channel$3.2M
- Interconnection of Caledon East and Palgrave Water System$1.4M
- Water servicing for the communities of Campbells Cross and Victoria in Town of Caledon$1.4M
- Resurfacing Highway 9 - West of Peel Road$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32220 in the federal list. How to read these figures.