Belfountain Conservation Area: Dam & Channel
Federal contribution
$3.2M
$3,200,000
Federal share80%
of $4.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 9, 2021
Built
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Credit Valley Conservation Authority
- Construction start
- Jun 17, 2021(actual)
- Construction end
- Dec 10, 2021(actual)
Against the original forecast
- Construction end3 weeks earlyforecast Dec 31, 2021
Also in Caledon
- Old Bolton Fire Hall revitalization into a low carbon, multi-purpose Community Hub as part of Caledon's downtown Bolton Revitalization Plan.$4.3M
- Interconnection of Caledon East and Palgrave Water System$1.4M
- Water servicing for the communities of Campbells Cross and Victoria in Town of Caledon$1.4M
- Resurfacing - on the Forks of the Credit Road from Hurontario Street to West$1.2M
- Resurfacing Highway 9 - West of Peel Road$1.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 60829 in the federal list. How to read these figures.