Warden Avenue Resurfacing
Federal contribution
$383,531
Federal share19%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Nov 9, 2010(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2009
- Construction end7 weeks earlyforecast Dec 31, 2010
Also in Markham
- City of Markhams Flood Control$48.6M
- Highway 404 - High Occupancy Vehicle Lanes$46.1M
- West Thornhill Flood Control on Three Streets with Structural Sewer Replacement in the City of Markham$4.5M
- Enhancing Health and Safety at City Facilities$4.2M
- Facility Accessibility, Energy Retrofit and Emergency Operations Centre Rehabilitation$2.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32241 in the federal list. How to read these figures.