Queen Street East

Springwater, Ontario

completeHighways and RoadsISF
Federal contribution
$437,383
Federal share27%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Township of Springwater
Construction start
Sep 15, 2009(actual)
Construction end
Oct 28, 2010(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Nov 1, 2009
  • Construction end8 weeks lateforecast Aug 30, 2010

Also in Springwater

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32243 in the federal list. How to read these figures.