Back to projects

Upgrade to Hillsdale Water Standpipe

Springwater, Ontario

completeDrinking WaterCWWF
Federal contribution
$83,892
Federal share35%

of $240.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 28, 2017
20182019
Built

Approved 8 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Township of Springwater
Construction start
Oct 26, 2017(actual)
Construction end
Dec 31, 2018(actual)

Against the original forecast

  • Construction start4 months lateforecast Jul 3, 2017
  • Construction end17 months lateforecast Jul 28, 2017

Also in Springwater

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 51203 in the federal list. How to read these figures.