Weston Road Resurfacing
Federal contribution
$307,546
Federal share23%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Regional Municipality of York
- Construction start
- Sep 1, 2009(actual)
- Construction end
- Nov 29, 2009(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2009
- Construction end4 months earlyforecast Mar 31, 2010
Also in Vaughan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32269 in the federal list. How to read these figures.