New Fire Station in North East Burlington
Federal contribution
$750,000
Federal share33%
of $2.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- City of Burlington
- Construction start
- Jul 13, 2010(actual)
- Construction end
- Oct 24, 2011(actual)
Against the original forecast
- Construction start3 months earlyforecast Sep 30, 2010
- Construction end3 weeks lateforecast Sep 30, 2011
Also in Burlington
- Halton Region Wastewater Treatment (Skyway Facility)$51.4M
- Replacement of Access Points; Open Concept Schools; Building Automation Systems & Controls Upgrade; Child Care Retrofits & Outdoor Spaces$6.9M
- Portable Classroom Ventilation Improvements; HVAC Improvements; Window Replacement$5.6M
- Improvements to HVAC, Windows, Bottle Filling Stations, Washrooms, Doors, Child Care Centre, WiFi and Network Infrastructure$5.4M
- Highway 403 - Rehabilitation and Resurfacing$4.1M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32322 in the federal list. How to read these figures.