Rehabilitation of Bayshore Road
Tyendinaga Mohawk Territory, Ontario
Federal contribution
$192,114
Federal share28%
of $684.3K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- County of Hastings
- Construction start
- May 30, 2010(actual)
- Construction end
- Jan 5, 2011(actual)
Against the original forecast
- Construction start8 weeks lateforecast Apr 1, 2010
- Construction end2 months lateforecast Oct 29, 2010