Back to projects

MBQ Elder Care Home

Tyendinaga Mohawk Territory, Ontario

underwayHealthcare InfrastructureGICB
Federal contribution
$25.0M
$25,000,000
Federal share33%

of $76.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 25, 2023
2023202420252026
BuiltForecast

Approved 8 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Aug 15, 2023(actual)
Construction end
Apr 30, 2026(forecast)

Against the original forecast

  • Construction start15 months lateforecast May 1, 2022

Also in Tyendinaga Mohawk Territory

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 64772 in the federal list. How to read these figures.