McCowan Road Reconstruction

Whitchurch-Stouffville, Ontario

completeHighways and RoadsISF
Federal contribution
$505,278
Federal share26%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
May 3, 2010(actual)
Construction end
Aug 31, 2010(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Sep 15, 2010

Also in Whitchurch-Stouffville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32379 in the federal list. How to read these figures.