Back to projects

Replacement of Stouffer Street watermain and sanitary sewer, and improvements to the storm sewer sytem

Whitchurch-Stouffville, Ontario

completeDrinking WaterCWWF
Federal contribution
$555,814
Federal share35%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 24, 2017
20182019
Built

Approved 2 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Construction start
Nov 1, 2017(actual)
Construction end
Jul 15, 2019(actual)

Against the original forecast

  • Construction start6 months lateforecast May 15, 2017
  • Construction end15 months lateforecast Mar 31, 2018

Also in Whitchurch-Stouffville