Back to projects

Combined Sewer Overflow High Rate Treatment - Niagara Falls Wastewater Treatment Plant

Niagara Falls, Ontario

completeWastewaterISF
Federal contribution
$4.6M
$4,572,476
Federal share30%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built

Approved 2 months after the announcement.

Program
Infrastructure Stimulus Fund
Construction start
Mar 29, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction end4 weeks lateforecast Sep 30, 2011

Also in Niagara Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32386 in the federal list. How to read these figures.