Niagara Parks Commission - War of 1812

Niagara Falls, Ontario

completeCultureISF
Federal contribution
$4.5M
$4,469,548
Federal share50%

of $8.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 12, 2010
2011
Built

Approved 6 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Niagara Parks Commission
Construction start
Aug 31, 2010(actual)
Construction end
Oct 31, 2011(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Jul 20, 2010

Also in Niagara Falls

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 39649 in the federal list. How to read these figures.