Wales Village Watermain Extension
Federal contribution
$288,662
Federal share31%
of $920.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
20102011
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Township of South Stormont
- Construction start
- Aug 24, 2009(actual)
- Construction end
- Mar 31, 2011(actual)
Against the original forecast
- Construction start2 months earlyforecast Nov 1, 2009