Community Parks - Pavilion
Federal contribution
$116,600
Federal share40%
of $291.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 29, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Township of South Stormont
- Construction start
- Sep 12, 2022(actual)
- Construction end
- Mar 3, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Jul 4, 2022
- Construction end3 months lateforecast Nov 30, 2022
Also in South Stormont
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58170 in the federal list. How to read these figures.