Schedule

Announced and approvedApr 29, 2021
20222023
Built

Approved 2 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Township of South Stormont
Construction start
Sep 12, 2022(actual)
Construction end
Mar 3, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Jul 4, 2022
  • Construction end3 months lateforecast Nov 30, 2022