Clairage Drive Reconstruction
Federal contribution
$1.1M
$1,102,063
Federal share18%
of $6.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
2010
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Town of Richmond Hill
- Construction start
- May 3, 2010(actual)
- Construction end
- Nov 30, 2010(actual)
Against the original forecast
- Construction start2 weeks lateforecast Apr 19, 2010
- Construction end4 months earlyforecast Mar 31, 2011
Also in Richmond Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 32407 in the federal list. How to read these figures.