Richmond Hill David Dunlap Observatory Park Pedestrian/Cyclist Bridge and Recreation Trail, Province of Ontario
Federal contribution
$3.2M
$3,180,000
Federal share60%
of $5.3M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 15, 2023
2023202420252026
BuiltForecast
Approved 9 months before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Town of Richmond Hill
- Construction start
- Oct 28, 2024(actual)
- Construction end
- Jan 31, 2026(forecast)
Against the original forecast
- Construction start6 months lateforecast May 1, 2024
Also in Richmond Hill
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 63655 in the federal list. How to read these figures.