Police/Fire Station Building Rehabilitation
Federal contribution
$28,293
Federal share28%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 5, 2009
ApprovedAug 17, 2009
Built
Approved 2 months after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of West Grey
- Construction start
- Aug 5, 2009(actual)
- Construction end
- Dec 7, 2009(actual)
Also in West Grey